Optimal Project Sequencing for Maximized Profit

DSA
hard

Optimal Project Sequencing for Maximized Profit

Hard
Greedy
Sorting
Scheduling

Overview

You are a project manager optimizing the workflow for a critical team. Your team can only work on one project at a time. Each project has a specific duration, a base profit it yields upon completion, and a unique "delay penalty rate." This penalty rate means that for every unit of time the team spends on other projects before starting the current one, the current project's base profit is reduced. Your objective is to sequence all available projects to maximize the total profit for your organization. This problem is crucial for resource allocation and strategic planning in fast-paced environments where delays have tangible costs.

What you need to do / Task

Implement a function maximizedProjectProfit that takes a list of projects and returns the maximum total profit achievable by optimally sequencing them.

  • Optimal Sequencing: Determine the best order to execute all given projects.
  • Profit Calculation: For each project in the chosen sequence, its effective profit is base_profit - (cumulative_time_spent_on_previous_projects * delay_penalty_rate). The cumulative time spent on previous projects is the sum of their durations.
  • Total Profit: The sum of effective profits of all projects in the optimal sequence.

Input & output

Input: projects: An array of objects/tuples, where each object/tuple represents a project and has the following structure:

  • duration: A non-negative integer representing the time required to complete the project.
  • profit: A non-negative integer representing the base profit gained upon completing the project.
  • penaltyRate: A non-negative integer representing the penalty rate per unit of time delayed.

Output: A single integer representing the maximum total profit that can be achieved.

Clarifications

  • All projects must be completed.
  • The duration, profit, and penaltyRate for any project will be non-negative.
  • The cumulative time for the first project in the sequence is 0, so its profit is simply base_profit.
  • The total profit can be negative if penalties exceed base profits significantly.

Examples

1

Example 1

Input:

projects = [{"duration": 1, "profit": 10, "penaltyRate": 5}, {"duration": 2, "profit": 20, "penaltyRate": 2}]

Output:

28

Note:

Let's denote projects as P1={D:1, P:10, R:5} and P2={D:2, P:20, R:2}. To maximize total profit, we need to sort projects by penaltyRate / duration in decreasing order. Note: If duration is 0, treat its penaltyRate / duration as effectively infinite, meaning it should be processed first among non-zero duration projects with finite duration, or before other zero-duration projects with higher penaltyRate. Ratio P1: R/D = 5/1 = 5. Ratio P2: R/D = 2/2 = 1. Greedy order: P1, then P2.

  • P1 (duration 1): Effective Profit = 10 - (0 * 5) = 10. Cumulative time after P1 = 1.
  • P2 (duration 2): Effective Profit = 20 - (1 * 2) = 18. Cumulative time after P2 = 1 + 2 = 3. Total Profit = 10 + 18 = 28.

If the order was P2, then P1:

  • P2 (duration 2): Effective Profit = 20 - (0 * 2) = 20. Cumulative time after P2 = 2.
  • P1 (duration 1): Effective Profit = 10 - (2 * 5) = 0. Cumulative time after P1 = 2 + 1 = 3. Total Profit = 20 + 0 = 20. Clearly 28 is better.
2

Example 2

Input:

projects = [{"duration": 3, "profit": 100, "penaltyRate": 10}, {"duration": 1, "profit": 10, "penaltyRate": 0}, {"duration": 2, "profit": 50, "penaltyRate": 20}]

Output:

150

Note:

Let's denote projects as P1={D:3, P:100, R:10}, P2={D:1, P:10, R:0}, P3={D:2, P:50, R:20}. To maximize total profit, we need to sort projects by penaltyRate / duration in decreasing order. Ratio P1: R/D = 10/3 ≈ 3.33. Ratio P2: R/D = 0/1 = 0. Ratio P3: R/D = 20/2 = 10. Greedy order (decreasing R/D): P3, P1, P2.

  • P3 (duration 2): Effective Profit = 50 - (0 * 20) = 50. Cumulative time after P3 = 2.
  • P1 (duration 3): Effective Profit = 100 - (2 * 10) = 80. Cumulative time after P1 = 2 + 3 = 5.
  • P2 (duration 1): Effective Profit = 10 - (5 * 0) = 10. Cumulative time after P2 = 5 + 1 = 6. Total Profit = 50 + 80 + 10 = 150.
3

Example 3

Input:

projects = [{"duration": 10, "profit": 100, "penaltyRate": 10}, {"duration": 10, "profit": 100, "penaltyRate": 10}]

Output:

100

Note:

Both projects have the same R/D ratio (10/10 = 1). The relative order between projects with identical ratios does not affect the total profit. Let's assume P1 is processed then P2.

  • P1 (duration 10): Effective Profit = 100 - (0 * 10) = 100. Cumulative time after P1 = 10.
  • P2 (duration 10): Effective Profit = 100 - (10 * 10) = 0. Cumulative time after P2 = 10 + 10 = 20. Total Profit = 100 + 0 = 100.

Constraints

Constraints & assumptions

  • 1 <= projects.length <= 10^5
  • 0 <= duration[i] <= 10^4
  • 0 <= profit[i] <= 10^9
  • 0 <= penaltyRate[i] <= 10^4
  • The sum of all durations will not exceed 10^9.
  • Intermediate profit calculations (e.g., cumulative_time * penalty_rate) might exceed standard 32-bit integer limits. Ensure your chosen language's number type can handle values up to 10^14 (e.g., JavaScript's number or C++/Java's long long/long).

What interviewers evaluate

  • Correctness of Greedy Strategy: Deriving and implementing the correct greedy choice for sequencing projects.
  • Algorithmic Efficiency: Optimal time and space complexity for processing N projects.
  • Edge Case Handling: Correctly handling scenarios like zero durations, zero profits, or zero penalty rates.
  • Code Structure & Readability: Clean, well-organized, and easy-to-understand code.

Loading editor...