Optimal Project Sequencing for Maximized Profit
You are a project manager optimizing the workflow for a critical team. Your team can only work on one project at a time. Each project has a specific duration, a base profit it yields upon completion, and a unique "delay penalty rate." This penalty rate means that for every unit of time the team spends on other projects before starting the current one, the current project's base profit is reduced. Your objective is to sequence all available projects to maximize the total profit for your organization. This problem is crucial for resource allocation and strategic planning in fast-paced environments where delays have tangible costs.
Implement a function maximizedProjectProfit that takes a list of projects and returns the maximum total profit achievable by optimally sequencing them.
base_profit - (cumulative_time_spent_on_previous_projects * delay_penalty_rate). The cumulative time spent on previous projects is the sum of their durations.Input:
projects: An array of objects/tuples, where each object/tuple represents a project and has the following structure:
duration: A non-negative integer representing the time required to complete the project.profit: A non-negative integer representing the base profit gained upon completing the project.penaltyRate: A non-negative integer representing the penalty rate per unit of time delayed.Output: A single integer representing the maximum total profit that can be achieved.
duration, profit, and penaltyRate for any project will be non-negative.base_profit.Examples
Example 1
Input:
projects = [{"duration": 1, "profit": 10, "penaltyRate": 5}, {"duration": 2, "profit": 20, "penaltyRate": 2}]
Output:
28
Note:
Let's denote projects as P1={D:1, P:10, R:5} and P2={D:2, P:20, R:2}.
To maximize total profit, we need to sort projects by penaltyRate / duration in decreasing order. Note: If duration is 0, treat its penaltyRate / duration as effectively infinite, meaning it should be processed first among non-zero duration projects with finite duration, or before other zero-duration projects with higher penaltyRate.
Ratio P1: R/D = 5/1 = 5. Ratio P2: R/D = 2/2 = 1.
Greedy order: P1, then P2.
If the order was P2, then P1:
Example 2
Input:
projects = [{"duration": 3, "profit": 100, "penaltyRate": 10}, {"duration": 1, "profit": 10, "penaltyRate": 0}, {"duration": 2, "profit": 50, "penaltyRate": 20}]
Output:
150
Note:
Let's denote projects as P1={D:3, P:100, R:10}, P2={D:1, P:10, R:0}, P3={D:2, P:50, R:20}.
To maximize total profit, we need to sort projects by penaltyRate / duration in decreasing order.
Ratio P1: R/D = 10/3 ≈ 3.33. Ratio P2: R/D = 0/1 = 0. Ratio P3: R/D = 20/2 = 10.
Greedy order (decreasing R/D): P3, P1, P2.
Example 3
Input:
projects = [{"duration": 10, "profit": 100, "penaltyRate": 10}, {"duration": 10, "profit": 100, "penaltyRate": 10}]
Output:
100
Note:
Both projects have the same R/D ratio (10/10 = 1). The relative order between projects with identical ratios does not affect the total profit. Let's assume P1 is processed then P2.
Constraints
1 <= projects.length <= 10^50 <= duration[i] <= 10^40 <= profit[i] <= 10^90 <= penaltyRate[i] <= 10^410^9.cumulative_time * penalty_rate) might exceed standard 32-bit integer limits. Ensure your chosen language's number type can handle values up to 10^14 (e.g., JavaScript's number or C++/Java's long long/long).N projects.Loading editor...