Curated Production Pipeline

Hard
Graph
Topological Sort
Kahn's Algorithm

Overview

Spotify's content pipeline involves numerous steps from initial recording to final release. To ensure a smooth and efficient workflow, and to meet crucial deadlines for high-priority tracks, it's essential to properly sequence these production tasks. This problem simulates a simplified version of such a pipeline, where tasks have dependencies and some are critical with specific completion deadlines.

What you need to do / Task

You are given a set of production tasks, their dependencies, and a list of critical tasks with associated deadlines. Your goal is to determine a valid ordering of tasks such that all dependencies are met, and all critical tasks are completed by their respective deadlines.

Input & output

  • numTasks: An integer representing the total number of unique production tasks, labeled from 0 to numTasks - 1.
  • dependencies: An array of pairs [fromTask, toTask], where fromTask must be completed before toTask can begin.
  • criticalTasks: An array of pairs [taskId, maxPosition], where taskId is a critical task that must appear at an index <= maxPosition in the final ordered sequence (0-indexed).

Return: An array of numbers representing any valid topological order of tasks that satisfies all dependencies and critical task deadlines. If no such order exists (due to a cycle or an unmet critical deadline), return an empty array [].

Clarifications

  • Task IDs are 0-indexed, from 0 to numTasks - 1.
  • If multiple valid task orders exist, any one of them is acceptable.
  • If dependencies is empty, tasks can be ordered arbitrarily, subject to criticalTasks constraints.
  • If criticalTasks is empty, only dependency constraints need to be satisfied.
  • The maxPosition for critical tasks is 0-indexed. So, a maxPosition of 0 means the task must be the very first task in the sequence.

Examples

1

Example 1

Input:

numTasks = 4, dependencies = [[1, 0], [2, 0], [3, 1], [3, 2]], criticalTasks = [[0, 3]]

Output:

[3,1,2,0]

Note:

A valid order is [3, 1, 2, 0]. Task 0 is critical and must be at position <= 3. It's at position 3, which satisfies the condition. Another valid output could be [3,2,1,0].

2

Example 2

Input:

numTasks = 3, dependencies = [[0, 1], [1, 2], [2, 0]], criticalTasks = []

Output:

[]

Note:

The dependencies form a cycle (0 -> 1 -> 2 -> 0), so no valid topological order can exist. An empty array is returned.

3

Example 3

Input:

numTasks = 4, dependencies = [[1, 0], [2, 0], [3, 1], [3, 2]], criticalTasks = [[0, 1]]

Output:

[]

Note:

In any valid topological order, tasks 1 and 2 must come before task 0, and task 3 must come before tasks 1 and 2. This means task 0 will always be at position 2 or 3 (e.g., [3,1,2,0] or [3,2,1,0]). Since task 0 is critical and must be at position <= 1, its deadline cannot be met. An empty array is returned.

4

Example 4

Input:

numTasks = 2, dependencies = [], criticalTasks = [[0, 0], [1, 1]]

Output:

[0,1]

Note:

No dependencies, so tasks can be ordered freely. Task 0 must be at position 0, Task 1 must be at position <= 1. The order [0, 1] satisfies both. The order [1, 0] would violate Task 0's critical deadline (1 <= 0 is false), so [0, 1] is the only valid sequence.

Constraints

Constraints & assumptions

  • 1 <= numTasks <= 10^5
  • 0 <= dependencies.length <= 2 * 10^5
  • 0 <= criticalTasks.length <= numTasks
  • All taskIds in dependencies and criticalTasks are valid: 0 <= taskId < numTasks.
  • 0 <= maxPosition < numTasks for all critical tasks.
  • Dependencies do not contain self-loops (e.g., [A, A]).
  • The graph formed by dependencies is not necessarily connected.

Out of scope

  • Finding the lexicographically smallest or any other "optimal" topological sort. Any valid sort is sufficient.
  • Input validation beyond the specified constraints (e.g., handling non-integer inputs).

What interviewers evaluate

  • Correctness: The solution must correctly identify cycles and unmet critical task deadlines, returning an empty array in such cases, and a valid sequence otherwise.
  • Algorithm Efficiency: The chosen algorithm should be efficient enough to handle large numbers of tasks and dependencies (optimal O(V+E) complexity).
  • Graph Representation: Effective use of data structures (e.g., adjacency lists, in-degree arrays) for graph representation.
  • Code Structure & Readability: Clean, well-organized code with appropriate variable names and comments where necessary.